AWS Data Center Dispute: Prokopiak, Santarsiero Pivot on Policy
State officials who publicly championed the $20 billion AWS project in June 2025 now support new disclosure laws for data centers.
By Leila Santos ·

The $20 billion Amazon Web Services investment in Pennsylvania infrastructure stands as the central figure in a growing political dispute in Lower Bucks County. The project is currently under construction at the former U.S. Steel site in Falls Township. This development has become a focal point for debates regarding energy usage, water consumption, and local governance.
State Rep. Jim Prokopiak and state Sen. Steve Santarsiero publicly celebrated the project's selection in June 2025. On June 9, 2025, Prokopiak praised the collaboration between state and local leaders that created a business-friendly environment for the investment. He described the arrival as just the beginning. Santarsiero was more explicit about his personal involvement. He stated he was proud of the role he played in reviving the Keystone Opportunity Zone at the steel property, a move he said paved the way for the data center construction.
Gov. Josh Shapiro reinforced this support two months later when he visited the future site. The administration used the visit to showcase the success of Pennsylvania's expedited permitting process. At that time, faster permitting and reduced regulatory hurdles were presented as key achievements for attracting private capital.
Public sentiment shifted after residents learned the full scale of the project. Concerns grew regarding the massive electricity requirements and the plan to use hundreds of natural-gas-fired generators. By 2026, public meetings in the area were packed with thousands of objectors. In response, Prokopiak began backing legislation that would require data centers to disclose energy and water consumption. Santarsiero joined efforts to establish strict, enforceable controls, including early disclosure of resource demands and stronger environmental protections.
Shapiro’s administration has also adjusted its stance. The governor removed data centers from the state’s fast-track permitting program. He now calls for greater transparency and community protections, a departure from the earlier emphasis on speed and investment attraction.
The timeline of public knowledge remains a point of contention. Falls Township approved a nondisclosure agreement in November 2024. By March 2025, public documents identified the site as a digital infrastructure campus, though Amazon’s identity and the full scope of the $20 billion investment were not disclosed until the June announcement. Residents argue that meaningful transparency requires information before decisions become difficult to reverse, rather than after construction begins.
The officials involved in the initial push for the project now support the very safeguards that were not in place during the permitting phase. Prokopiak and Santarsiero have not issued a formal retraction of their earlier statements. The public record shows they actively facilitated the project's arrival before the current wave of legislative proposals emerged.
Source: WBCB